The work consisted of the replacement of the Brookside Road Wastewater Pump Station along with support equipment and accessories as shown and specified. Temporary bypass pumping was maintained throughout the duration of the 30 ft deep wet well and pump chamber vault in a residential neighborhood. The project also included the installation of a new generator and telecommunication system. The project testing, commissioning, and start-up was completed within the project specification requirements.