Pump Station, Water Main Installation, Storage Tank – Dunstable, MA

Resident project representative overseeing installation of 12-inch DI water main and all residential and some commercial services, hydrant and sprinkler loops. Numerous test pits in various locations on rt. 113 were required to determine exact routing and potential conflicts. The project included a new pump station and large welded water storage tank and foundation.

Water Treatment Facility Improvements – Devens, MA

ECI provided oversight for two new PFAS WTF in Devens MA. The major proposed work under this contract includes Civil site work including land clearing, erosion control, earthwork, drainage, grading, site process piping, site utilities, site lighting, pavement, gravel drives, hot mix asphalt pavement, chain-link fence and gates, and utility structures; Site demolition including pavement, Continue Reading

Burlington New PFAS Building + Pump Station

The Mill Pond Treatment Plant Upgrades project includes the installation and construction of a brand new PFAS Building as well as a new Transfer Pump Station which contains an underground Clearwell for finished water. Each of the two new buildings are tied into the existing Mill Pond Water Treatment plant as well as the existing Continue Reading

WWTF Improvements (Fall River, MA)

Senior resident project representative that oversaw the demolition, addition and reconstruction of the plants sludge handling building installation. Sludge handling building had two new centrifuges and two new gravity belt filter presses installed. The project required 40’ diameter sludge holding tanks to be constructed with mixers, pumps and covers. We also removed and replaced five Continue Reading

WRRF Project (Littleton, MA)

Resident project representative oversaw the construction of 2 bioreactors, 2 equalization tanks, 1 influent pump station, 2 influent bar screens/wash presses, 3 new sludge storage tanks, and 1 process building. Resident project representative also oversaw the sitework, concrete and rebar installation, as well as all leak testing for tanks. Project included installation of mechanical equipment Continue Reading

Wachusett Dam Lower Gate House Pipe Replacement and Electrical Upgrades (Southborough, MA)

Full time on-site Resident Project Representative overseeing the coordination of demolition for existing swtichgear, transformers, generators, and associated wiring. Installation of extensive new Electrical Duct Banks, new 1’380 volt O/H Electrical Service, new pads and transformers and switchgear with new generators and new U/G natural gas service. Select site asphalt milling and repaving. Electrical manholes Continue Reading

Morris Ave. Wastewater Treatment Facility Upgrade (Bridgewater, MA)

Resident Project Representative’s Work Included: Improvements to the existing Bridgewater Wastewater Treatment Facility. The major proposed work under this contract includes Civil site work including land clearing, erosion control, earthwork, drainage, grading, site process piping, site utilities, site lighting, pavement, gravel drives, hot mix asphalt pavement, chain-link fence and gates, and utility structures; Site demolition Continue Reading